STACK Infrastructure NVA02

Compute capacity
61.1K H100e
IT power
85 MW
Capital cost
$3.2B

STACK Infrastructure NVA02 is an AI data center, located in the United States (9590 Hornbaker Rd, Manassas, VA 20109).

The site holds roughly 61,142 H100-equivalents of AI compute. It draws about 85 MW of power. Building and equipping it represents an estimated $3.2B of capital in 2025 dollars. It currently runs H100.

These figures are modelled estimates, not disclosures: Epoch AI derives them from permits, satellite imagery and reported spending, with an uncertainty of roughly 1.4x to 1.6x depending on the metric.

Timeline
0125.3K250.6K2019-10-19: 02024-10-01: 61.1K2026-02-14: 61.1K2028-01-01: 250.6K2019-10-192028-01-01
Compute (H100e): 0 (2019-10-19) → 250.6K (2028-01-01)
Full record
Country
United States
Location
9590 Hornbaker Rd, Manassas, VA 20109
H100 equivalents
61,142
Power
85 MW
Total capital cost
$3.2B
Current chips
H100
All chips
H100