Compute capacity
283.7K H100e
IT power
279 MW
Capital cost
$11B

Google Bristow is an AI data center operated by Google, located in the United States (13001 Rollins Ford Road, Bristow, VA 20136). Its compute is used by Google DeepMind.

The site holds roughly 283,675 H100-equivalents of AI compute. It draws about 279 MW of power. Building and equipping it represents an estimated $11B of capital in 2025 dollars. It currently runs TPU v5e, TPU v5p, TPU v6e, TPU v7.

These figures are modelled estimates, not disclosures: Epoch AI derives them from permits, satellite imagery and reported spending, with an uncertainty of roughly 1.4x to 1.6x depending on the metric.

Timeline
0141.8K283.7K2021-07-01: 02024-04-29: 49.9K2025-04-29: 171K2026-05-20: 283.7K2021-07-012026-05-20
Compute (H100e): 0 (2021-07-01) → 283.7K (2026-05-20)
Full record
Owner
Google
Users
Google DeepMind
Country
United States
Location
13001 Rollins Ford Road, Bristow, VA 20136
H100 equivalents
283,675
Power
279 MW
Total capital cost
$11B
Current chips
TPU v5e, TPU v5p, TPU v6e, TPU v7
All chips
TPU v5e, TPU v5p, TPU v6e, TPU v7